Please note that construction schedules are subject to change due to weather, site issues, etc.

Unsure about which is your area? Visit the Blueprint map and type in your address to find out!

Reference this MAP to view the impacted construction areas for next week.

  • Schreyer Springs
    • Newcomer will finish up the concrete work (curbs, chutes, gutters and driveway aprons.).
    • Remaining rain gardens that need planting will begin on 5/14/18
    • Asphalt paving and driveway aprons will begin the week of 5/21/18
    • There will be a separate crew, BLD who will be onsite working on the lateral lining
    • Schreyer Springs is nearing completion!
  • Weisheimer Indian Springs Pervious Paving Project
    • E Dominion has been closed to through traffic as of April 2nd.
    • There will be a crew installing the new curbs and driveway aprons. Residents who will have their driveways done have been notified by the crew
    • Crews will continue on the west end and work their way east. Though the road will be closed during this work, pedestrian access will be maintained.
      • E Dominion residents have been mailed notices regarding more details about the construction process and expected impacts. Please contact us if you live on this street and have physical limitations that will hinder you from walking to your home from a 3-house distance.
    • Foster Rd Pervious Paving (parking lane only) will begin on June 4.
  • Weisheimer Indian Springs Rain Gardens
    • Final restoration activities on rain gardens will begin May 14th, 2018. This includes planting, regrading, laying sod, and general site cleanup.
  • Blenheim Glencoe
    • There will be two crews working in the area on  Acton and Northridge completing the water service and storm work.
      • Northridge Rd.- between Foster and High
      • Acton Rd.-between Sharon Rd. and Granden Rd.
      • Waterline work will be done in the alley west of High St. between Erie and Webster
  • Facemeyer, who is the sub-contractor for Eramo, will be onsite to seed and mulch the areas that have already received topsoil
  • Overbrook Chatham
    • A crew will continue working on the storm sewer on Glenmont and Wynding
    • A second crew will start working on the storm sewer on Blenheim Rd. next
    • Storm sewer work will occur first, then curb/sidewalk work. Rain garden excavation for this area will begin in mid-April. Notices will be provided to residents 1-week in advance of crews mobilizing on your street, and an additional 48-hour notice for work in front of your house.
  • Morse Dominion
    •  There will be a crew working on E. Jeffery Pl and E. Royal Forest Blvd.  where they will be working on the lowering of the water main (affected residents have been notified by the crew if their water will be disrupted).
  • Basins will continue to be dug and installed on E. Dominion Blvd.

Please contact 614-645-1253 or blueprint@columbus.gov with any questions you may have.

Sump Pump inspections are being conducted in all active areas. Contact our outreach team if you are interested in learning more about our free sump pump program!

 