  • Schreyer Springs
    • Crew will be completing rain gardens on Eastlea Dr.
    • Newcomer will be on site working on concrete work on Eastlea Dr. (curbs, chutes, gutters and etc.)
    • Schreyer Springs is nearing completion!
  • Weisheimer Indian Springs Pervious Paving Project
    • E Dominion has been closed to through traffic as of April 2nd.
    • Storm sewer work will begin at the intersection of E Dominion and Shields Place, followed by waterline lowering. If your water service will be disrupted, you will receive a 48-hour advance notice.
    • Excavation will begin on west end of E Dominion. The temporary asphalt path will be installed prior to excavation.
    • Crews will begin on the west end and work their way east. Though the road will be closed during this work, pedestrian access will be maintained.
      • E Dominion residents have been mailed notices regarding more details about the construction process and expected impacts. Please contact us if you live on this street and have physical limitations that will hinder you from walking to your home from a 3-house distance.
    • Foster Rd Pervious Paving (parking lane only) will begin on June 4.
  • Weisheimer Indian Springs Rain Gardens
    • Repaving work on streets that received rain gardens will begin on or after April 15 (weather permitting). Notices will be provided to residents in advance of the work.
    • Final restoration activities on rain gardens will begin in May. This includes planting, regrading, laying sod, asphalt restoration, and general site cleanup.
  • Blenheim Glencoe
    • There will be multiple crews working on Glencoe, Acton, and Northridge completing the water service and storm work.
      • Fallis Rd.-working on the storm sewer
      • Northridge Rd.- between Foster and High
      • Acton Rd.-between Foster Rd and 270 Acton
      • Street light relocations will begin on the east end of Acton Rd
    • Concrete work (curbs/driveway aprons) will take place on Glencoe and Richards Rd
  • Overbrook Chatham
    • A crew will be completing the water service transfers on Wynding Dr. and Yaronia
    • A crew will begin working on the storm sewer on Glenmont
    • Tree clearing will begin first week of April. Residents have been notified about individual tree conflicts.
    • Storm sewer work will occur first, then curb/sidewalk work. Rain garden excavation for this area will begin in mid-April. Notices will be provided to residents 1-week in advance of crews mobilizing on your street, and an additional 48-hour notice for work in front of your house.
  • Morse Dominion
    •  There will be a crew working on Garden Rd. doing water service tie-ins (affected residents have been notified by the crew if their water will be disrupted).
    • There will be a second crew that will be working on E. Jeffery PL working on water service transfers and on Garden Rd.
      • Garden Rd will have a water shut off on Tuesday.
  • Basins will begin getting constructed on E. Dominion Blvd
    • Crews may move to  Beechwold depending of the progress made on the current streets.

 

Please contact 614-645-1253 or blueprint@columbus.gov with any questions you may have.

Sump Pump inspections are being conducted in all active areas. Contact our outreach team if you are interested in learning more about our free sump pump program!

 