Cooke Glenmont

  • They will be working on all outstanding follow up items in the coming weeks

Schreyer Springs

  • Facemeyer will be on Springs Dr W completing basin excavation
  • Preparation of Fairoaks Dr., no excavation will occur this week

Pervious Pavement

  • Residents on Cooke Rd and Henderson will experience a water shut off Wednesday September 6th from 3:00am-6:00am. Workers will be onsite as early as 2:00am to start working
  • Dixon Ct. will have road milled on Tuesday and continued activity the duration of the week

Weisheimer-Indian Springs Area:

  • Rain Garden Construction will begin in early September. Detailed schedule will be provided once confirmed with the contractor.
  • Columbia Gas will continue to work on Fairlawn this week.

Blenheim-Glencoe Area:

  • Construction is expected to begin in October. Detailed schedule will be provided once confirmed with the contractor.

Overbrook-Chatham Area:

  • Construction is expected to begin in October. Detailed schedule will be provided once confirmed with the contractor.

Morse-Dominion Area:

  • Construction is expected to begin in October. Detailed schedule will be provided once confirmed with the contractor.
  • Columbia Gas is working in this area through September.

For questions or concerns regarding Columbia Gas/Miller Pipeline work, please contact Kristin Begg, External Affairs Specialist for Columbia Gas of Ohio, (614) 460-5464 or kbegg@nisource.com.